Wednesday, June 28, 2017

Community Progress Update


As everyone knows the community is completing the final leg of the deck refurbishment project.  Please,  if anyone has any issues with the decks let Mary Jo at AA know, or contact a board member.  We have had very limited issues with the decks so far. 

We have completed over half the decks so far and should be wrapped up sometime in early July.  The rain in May slowed the project down but they will be done soon.    

 

In addition, we have completed the following tasks in the community

 

Painted and restored the pergola by the pool

Re-did the grounding and electric work at the pool

Restored the in ground pool lighting

Restored the pool bathroom emergency lighting

Trimmed trees and removed dead trees throughout the community
 
Addressed the mosquito issue by hiring an pest control expert to spray and control for mosquitos and other bugs over the summer

 

We are preparing to

 

Restore the pool bathroom floors

Replace the ADA mats at the corners

Replace the pool ladders and handles

Refurbish the fences around the ponds

 
 

If there are any issues in the community please let us know, you, all our neighbors are the eye and ears of the community.  We thank the folks who already help out.  And as always please address any home issues directly to AA. 

 

Thanks for your help and cooperation