Tuesday, July 24, 2012

Updated powerwashing and painting schedule

Given the very hot weather and intense rain the painting and powerwashing schedule has been revised here is the new schedule (subject to change). 

Below is the schedule for the power washing, painting and staining of deck schedule.  Section 3 is to begin next week.  Homeowners in Section 1- 1-15 Seabreeze, please insure your decks are clear of everything by July 23.  The contractor needs to finish the staining of those decks on Monday.  We appreciate your cooperation



ADDRESSES
POWER WASHING SCHEDULED
1-15 SEA BREEZE -ODD SIDE
WEEK OF JUNE 25 INTO WEEK OF JULY 2
76-92 WINDWARD-EVEN SIDE
WEEK OF JULY 9TH INTO WEEK OF JULY 20
56-72 WINDWARD-EVEN SIDE
SECTION 3
1-15 BAY BREEZE-ODD SIDE
SECTION 4
2-16 BAY BREEZE-EVEN SIDE
SECTION 5
22-36 WINDWARD -EVEN SIDE
SECTION 6
2-18 WINDWARD- EVEN SIDE
SECTION 7
39-55 WINDWARD- ODD SIDE
SECTION 8
73-83 WINDWARD- ODD SIDE
SECTION 9
97-109 WINDWARD-ODD SIDE
SECTION 10
115-131 WINDWARD- ODD SIDE
SECTION 11
106-122 WINDWARD- EVEN SIDE
SECTION 12
2-16 SEA BREEZE - EVEN SIDE
SECTION 13